Construction Updates
Construction Updates
(Updated July 2026)
Pre-Construction Work: April to Dec 2025
WORK COMPLETED: Involved temporary road closures between Craig Street and Susan Campbell Park to demolish the old Harbormaster Building and conduct utility and electrical work.
Phase 1/1A and Access/Staging:
Nov 2025 to May 2027 involves the closure of lower Dock Street between Craig Street and Susan Campbell Park and a partial closure of upper Dock Street between Craig and Randall Streets for heavy infrastructure work.
City Dock Park, Burtis House and Maritime Welcome Center:
Feb 2026 to July 2027 (projected timeline) work will involve the creation of the City Dock Park and amenities, rehabilitation of historic Burtis House and construction of the Maritime Welcome Center.
Phase 2:
May 2027 to March 2028 (projected timeline) will involve the closure of upper Dock Street between Randall Street and Craig Street. Includes resilience work at the top of Ego Alley, working around toward Compromise Street
Deliveries, Pick-ups and Trash Collection
Delivery location will be designated along Upper Dock Street
Deliveries for lower Dock Street will be accessed via Lower Prince George Street
Trash bins will be emptied more frequently to minimize odor and overflow
The actual location of trash bins may change as needed to accommodate the construction process.
Noise, Dust, and Disruptions
The contractor is responsible for keeping work site clear of debris
The contractor will work with Annapolis Police to provide security of the construction site
The contractor will work with the Department of Public Works to remove construction debris that may make its way outside of the fenced perimeter
Contractor will relay information to business liaison who will make information available for distribution
Hours of construction will be Monday to Saturday, 7 a.m. to dusk. Exceptions to these hours may occur if approved by the Department of Public Works (DPW) with prior notice.
Pedestrian Access During Construction
Provide access to Ego Alley boardwalk and Watermark Cruises
Throughout construction, Dock Street businesses will be fully accessible to customers
Wayfinding to help customers will be well marked
Customer pick up and drop off will remain available along Upper Dock Street
City Dock Planning & Construction